53 East of Gamston/North of Tollerton Development Framework Supplementary Planning Document
PDF 225 KB
The report of the Director – Development and Economic Growth is attached.
Additional documents:
Decision:
It was RESOLVED that Cabinet:
a) continues to support the principle of a Development Framework Supplementary Planning Document (SPD) for the Gamston/Tollerton Sustainable Urban Extension;
b) pauses the current SPD approval process in response to comments made to the public consultation, whilst more detailed information is requested on highways, especially the connectivity of the site to and across the A52.
c) requests the Leader of the Council to write to:
· the site owners/developers/promoters, including Nottinghamshire County Council as landowner of part of the site, to ask them to urgently provide the outstanding highways solution; and
· Nottinghamshire County Council as Highways Authority and National Highways to work proactively and at pace to reach a satisfactory highways solution;
so that this SPD can be brought back to Cabinet by 10 March 2026 for further consideration;
d) requires that any further detailed highways and Infrastructure Delivery Plan information is published for public consultation if appropriate;
e) considers any future recommendations made by the Local Development Framework Group; and
f) thanks Council officers and others for the significant amount of work that has been done.
Minutes:
The Cabinet Portfolio Holder for Planning and Housing, Councillor Upton, presented the report of the Director – Development and Economic Growth, which detailed the East of Gamston/North of Tollerton Development Framework Supplementary Planning Document.
Before Councillor Upton introduced the item, the Leader advised that this report was not seeking to grant approval of any planning application, it was to consider approval of a framework, under which planning applications would be determined in the future. Matters including potential flooding and land contamination would be considered during the planning application process, they were not part of this particular process.
Councillor Upton referred to the significant public interest generated in the proposed redevelopment and reiterated the Leader’s comments. It was noted that in 2014 this strategic site was adopted as part of the Rushcliffe Local Plan Part 1 for around 4,000 new homes, employment land and supporting infrastructure. The site was also included in the draft Greater Nottingham Strategic Plan, which would be publicly examined in the Spring. Councillor Upton stated that during the last 11 years, discussions had taken place involving the Council, various consultees and stakeholders to develop a single-site Masterplan; however, progress had been slow, and limited to the last few years, resulting in the production of a Development Framework Supplementary Planning Document (SPD). It was not necessary to have a Masterplan or an SPD; however, the Council felt that it was better to have a Plan, to coordinate development and avoid random development without any site planning. Councillor Upton confirmed that the SPD had been considered and unanimously supported at the cross-party Local Development Framework Group meeting last week. He advised that the SPD had to be approved by 30 June, to avoid the Government’s cut off date, missing that deadline would delay the process, causing significant delay to this site’s vital contribution to maintaining the Borough’s five year housing supply, which the Council required to manage development in the Borough. Councillor Upton stated that without the five year supply, the Council could not resist unplanned development, which had happened before, and it would also allow developers to submit appeals to the Planning Inspectorate for non-determination. He referred to the National housing crisis and the Government’s ambition to build 1.5 million homes during this Parliament.
Nevertheless, Councillor Upton advised that the Council had listed to comments made following the public consultation, and it was proposed that the decision to adopt the SPD should be paused, to request more detailed information and he proposed the following revised recommendation:
It is RECOMMENDED that Cabinet:
a) continues to support the principle of a Development Framework Supplementary Planning Document (SPD) for the Gamston/Tollerton Sustainable Urban Extension;
b) pauses the current SPD approval process in response to comments made to the public consultation, whilst more detailed information is requested on highways, especially the connectivity of the site to and across the A52;
c) requests the Leader of the Council to write to:
· the site owners/developers/promoters, including Nottinghamshire County Council as landowner of part of ... view the full minutes text for item 53